A deadline can be set for a task. This deadline MUST be
consistant with task start date against task estimated duration
:
- If start date is defined, deadline cannot occur before the
start date summed with expected duration.
- If start date is not enabled, it will nevertheless be
calculated automatically as deadline minus the expected duration (0
as default for duration).
- If the task is assigned to a dated milestone, deadline cannot
overcome milestone deadline.
- Deadline cannot overcome project end date.